    Infrascope 2025/26

    Panama

    Score: 59.3
    out of 100
    Rank: 9th
    out of 26 countries

    Despite having one of the region's more developed public-private partnership (PPP) regulatory frameworks, the country has been relatively slow to translate its institutional strengths into projects under the 2019 law. Recent progress on major highway PPPs marks an important turning point, demonstrating the framework's growing practical application. Sustaining this momentum will require continued improvements in project preparation, financing support and performance evaluation.

    PAN_name
    MACRO ENVIRONMENT
    Population, 20254.6m
    Source: The Economist Intelligence Unit
    GDP (US$), 2025$90.7bn
    Source: The Economist Intelligence Unit
    Sovereign risk rating, Oct 2026BBB-
    Source: S&P Global Ratings
    PPP INVESTMENT
    Number, 2016-25*8
    Source: IJ Global‡
    Total (US$), 2016-25$3.2bn
    Source: IJ Global‡
    % of all infrastructure investment, 2016-25†10%
    Source: IJ Global,‡ Infralatam, Economist Enterprise
    PPP INVESTMENT BY SECTOR (US$), 2016-25
    Transport
    Transport$2.9bn
    Renewables
    Renewables$0.1bn
    Energy (non-renewables)
    Energy (non-renewables)$0.2bn
    Source: IJ Global‡
    * Number of projects that reached financial close, including subnational projects. † Value of infrastructure PPPs (see definition in IJ Global footnote) divided by total infrastructure spending (estimated using Infralatam’s public sector estimates and Economist Impact calculations), averaged over the past ten years. ‡ Source: IJ Global, cross-checked with the World Bank PPI database. Data may include projects that are developed under PPP, sectoral or concession laws, with differences among countries. Focuses on greenfield and brownfield projects; excludes asset acquisition, company acquisition, securitization and refinancing transactions.
    Policies and institutions
    Panama's dedicated PPP framework was established by Law 93 of 2019 and Executive Decree 840 of 2020.1 The National PPP Secretariat provides technical support to contracting agencies, while a governing body oversees key decisions. However, the framework operates alongside the older administrative concessions regime under Law 5 of 1988.2 This overlap allows functionally similar projects to be structured under different procurement, appraisal and oversight requirements, potentially reducing regulatory consistency and predictability for investors.3 Recent refinements include new project eligibility and technical assessment manuals in 20244 and Executive Decree 58 of 2025, which streamlined preparation procedures for certain projects.5
    Recent market developments
    Panama has considerable experience with private infrastructure investment, but implementation under its dedicated PPP framework is relatively recent. The Pan-American Highway East project, awarded in 2024, began construction in 2025 and secured financing exceeding US$281m in January 2026.6 The Pan-American Highway West project also advanced, receiving its order to proceed in May 2026, with an estimated investment of US$312m.7 The government subsequently authorized procurement of the US$606.5m Centenario Highway project,8 while the proposed maximum-security prison PPP received approval to advance toward tendering.9 Other initiatives, including electricity transmission, remain under preparation.10 These developments signal growing activity, although the pipeline has yet to translate into a sustained flow of completed PPP transactions.
    Political and public support
    Political support for PPPs has remained relatively consistent across administrations, with the 2019 framework maintained and progressively refined. The current administration (2024 to present) has demonstrated continued commitment through the advancement of major highway projects and efforts to expand the pipeline.11,12 The framework also received legislative support when enacted in 2019, although recent evidence of explicit multiparty endorsement is limited. No sustained opposition specifically targeting PPPs has been identified. In September 2026, the government introduced legislation to streamline PPP procedures and extend the framework's application to additional public institutions, including the national water utility and Social Security Fund.13
    Notable strengths
    Panama's principal strengths lie in the regulations and institutions category and the risk management and contract monitoring category, both ranking 5th regionally. Its dedicated PPP institutions, interagency coordination and competitive procurement procedures rank among the region’s strongest, while structured project selection processes contribute to its relatively strong performance in this area. The framework also provides relatively strong contractual risk allocation mechanisms, contingent-liability management and lenders’ step-in rights, alongside contractual protections against adverse government actions.
    Notable challenges
    Panama's environmental and social sustainability requirements remain relatively weak, particularly regarding climate resilience and social equitability in project selection. The absence of dedicated project development and viability gap funds also limits support for project preparation and implementation. Despite a relatively developed financial environment, fewer tendered projects have reached financial close in recent years, highlighting challenges in converting opportunities into financed transactions. Finally, Panama lacks systematic ex-post evaluation of operational PPPs, limiting opportunities for institutional learning.
    Recent progress
    Panama has made progress on translating its PPP framework into project implementation, with the advancement of major highway concessions under the 2019 law. Contract transparency has also improved through the publication of periodic reports on ongoing PPP projects, providing greater visibility into implementation and government commitments. New technical guidance issued in 2024 and regulatory amendments in 2025 have also refined project preparation procedures, helping to strengthen the framework as the country gains experience implementing PPPs.

    Top five recommendations for progress

    (ordered according to index category)

    1
    Clarify the scope of existing PPP and concession legislation
    Establish clear criteria for determining when infrastructure projects should be procured under the 2019 PPP law or the 1988 concessions law. Clarifying their respective scopes would address demonstrated regulatory ambiguity and improve consistency and predictability in project preparation and procurement.
    Timeline to achieve
    Medium term
    Difficulty to achieve
    Medium
    Impact on category 1: Regulations and institutions
    Panama: current score
    94.8
    Score with recommendation applied
    95.8
    020406080100
    2
    Strengthen methodologies and tools for project appraisal
    Develop a published methodology for fiscal affordability assessments and standardized tools to support cost-benefit, fiscal affordability and value-for-money assessments. Building on existing guidance, these measures would improve consistency in project appraisal, facilitate comparisons across proposals and strengthen evidence-based investment decisions.
    Timeline to achieve
    Medium term
    Difficulty to achieve
    High
    Impact on category 2: Project preparation and sustainability
    Panama: current score
    51.5
    Score with recommendation applied
    55.2
    020406080100
    3
    Establish dedicated PPP project support funds
    Establish and capitalize dedicated project development and viability gap funds to support PPP preparation and implementation. These mechanisms would help finance feasibility studies, improve project bankability and support socially beneficial infrastructure projects that may not be commercially viable without public contributions.
    Timeline to achieve
    Long term
    Difficulty to achieve
    High
    Impact on category 2: Project preparation and sustainability
    Panama: current score
    51.5
    Score with recommendation applied
    64.0
    020406080100
    4
    Integrate social inclusion and resilience into PPP project preparation
    Incorporate explicit criteria for climate resilience, social inclusion, gender equality, employment and small-business participation into PPP selection and preparation. These requirements would complement existing environmental safeguards and help ensure that infrastructure investments address broader development priorities and community needs.
    Timeline to achieve
    Short term
    Difficulty to achieve
    Low
    Impact on category 2: Project preparation and sustainability
    Panama: current score
    51.5
    Score with recommendation applied
    70.2
    020406080100
    5
    Require and formalize ex-post evaluation of PPP projects
    Require ex-post evaluations, designate a responsible independent institution and establish a standardized methodology for assessing operational PPPs against their original objectives, costs and outcomes, including risk performance and value for money. Require evaluation findings to inform subsequent project selection, preparation and contract management.
    Timeline to achieve
    Medium term
    Difficulty to achieve
    Medium
    Impact on category 5: Performance evaluation and impact (ex-post)
    Panama: current score
    26.5
    Score with recommendation applied
    47.1
    020406080100
    Assessment guidance:
    Short term: achievable in months (ie, straightforward activities such as procedural updates)
    Medium term: up to a year (ie, moderately involved activities such as building web platforms)
    Long term: more than a year (ie, time-consuming activities such as new legislation/institutions)
    Difficulty/complexity: rated as low/medium/high—often mirrors the time frame, but can differ based on how technical it is, how many resources are needed and how politically challenging it is, etc.
    1. https://www.gacetaoficial.gob.pa/pdfTemp/28864_B/74982.pdf
    2. https://infojuridica.procuraduria-admon.gob.pa/norma_screen?numsec=20721
    3. https://www.presidencia.gob.pa/publicacion/gabinete-da-luz-verde-para-estudios-y-seleccion-de-concesionario-del-teleferico
    4. https://enterector.gob.pa/resoluciones-emitidas-3/
    5. https://www.presidencia.gob.pa/publicacion/el-gobierno-nacional-refuerza-la-transparencia-del-proceso-licitatorio-del-proyecto-app-de-la-carretera-panamericana-oeste-con-la-aprobacion-de-la-adenda-no-5
    6. https://www.rutadeleste.pa/panama-acredita-el-cierre-financiero/
    7. https://www.presidencia.gob.pa/index.php/publicacion/presidente-mulino-entrega-orden-de-proceder-para-la-rehabilitacion-de-la-via-panamericana-oeste-desde-loma-campana-hasta-santiago-
    8. https://www.presidencia.gob.pa/publicacion/autorizan-licitacion-de-proyecto-app-para-modernizar-la-autopista-centenario-inversion-de-b-606-5-millones-que-generara-mas-de-12-mil-empleos
    9. https://enterector.gob.pa/proyecto-centro-penitenciario-de-maxima-seguridad/
    10. https://enterector.gob.pa/resoluciones-emitidas-3/
    11. https://www.presidencia.gob.pa/index.php/publicacion/presidente-mulino-entrega-orden-de-proceder-para-la-rehabilitacion-de-la-via-panamericana-oeste-desde-loma-campana-hasta-santiago-
    12. https://www.presidencia.gob.pa/publicacion/autorizan-licitacion-de-proyecto-app-para-modernizar-la-autopista-centenario-inversion-de-b-606-5-millones-que-generara-mas-de-12-mil-empleos
    13. https://asamblea.gob.pa/Noticias/Legislativa/EJECUTIVO-PRESENTA-MODERNIZACION-DEL-REGIMEN-DE-APP

    Infrascope 2025/26

    Score 0–100 where 100 = best, rank out of 26 countries

    Nascent

    0 to <30

    Emerging

    30 to <60

    Developed

    60 to <80

    Mature

    80 to 100
    0102030405060708090100
    Infrascope 2025/26