Infrascope 2025/26
Mexico
Score: 60.4
out of 100
Rank: 8th
out of 26 countries
An experienced public-private partnership (PPP) market with relatively sophisticated project preparation and financing capabilities, Mexico has nevertheless seen limited new project activity in recent years. The government's renewed infrastructure investment agenda seeks to mobilize private capital through mixed-investment arrangements and traditional PPPs, reflecting a preference for greater public control. This marks a significant shift in how Mexico intends to harness private participation in infrastructure development.
MACRO ENVIRONMENT
Population, 2025131.9m
Source: The Economist Intelligence UnitGDP (US$), 2025$1.8trn
Source: The Economist Intelligence UnitSovereign risk rating, Oct 2026BBB
Source: S&P Global RatingsPPP INVESTMENT
Number, 2016-25*67
Source: IJ Global‡Total (US$), 2016-25$17.7bn
Source: IJ Global‡% of all infrastructure investment, 2016-25†11%
Source: IJ Global,‡ Infralatam, Economist EnterprisePPP INVESTMENT BY SECTOR (US$), 2016-25
Transport$5.2bn
Renewables$7.7bn
Energy (non-renewables)$1.8bn
Water and waste$0.1bn
Social infrastructure$0.6bn
Digital infrastructure$2.3bn
Policies and institutions
Mexico has an established PPP framework at federal and state levels, anchored by the Public-Private Partnerships Law (2012). The Ministry of Finance's Investment Unit oversees project appraisal and approval, while the National Infrastructure Fund supports project preparation and financing. A significant reform came in April 2026, when the government enacted the Law for the Promotion of Investment in Strategic Infrastructure for Development with Wellbeing, followed by implementing regulations in May.1,2 The new framework enables public, private and social-sector participation in strategic infrastructure, permitting varying degrees of public ownership. However, it operates alongside existing PPP and sectoral frameworks, creating overlapping legal and procurement routes for some functionally equivalent PPP-type projects.
Recent market developments
Mexico has substantial experience with privately financed infrastructure, particularly in transport and renewable energy, but conventional PPP activity has slowed in recent years. Projects with recent financing transactions include the Las Varas-Puerto Vallarta highway in 2023 and the Los Cabos desalination plant in 2024, with limited subsequent activity recorded in available project data.3 The government has nevertheless announced an ambitious infrastructure investment agenda, including 18 highway projects involving mixed-investment arrangements or construction, maintenance, rehabilitation and operation contracts4 in March 2026.5 Some of these arrangements exhibit characteristics of PPPs, including long-term private operational responsibilities and risk sharing. The projects form part of a broader Ps5.6trn investment plan through 2030.6
Political and public support
The current administration (2024 to present) has reaffirmed its commitment to private infrastructure investment, while prioritizing mixed-investment arrangements, including PPP-compatible models, over traditional PPP contracts. The president has criticized earlier PPP arrangements for their perceived fiscal costs and advocated discontinuing their use in certain contexts.7 Nevertheless, the government has published a substantial pipeline of projects involving private participation,8 and several political parties have demonstrated support for PPPs or alternative partnership models.9 Mexico therefore combines an active agenda for private infrastructure participation and multiparty support with meaningful political opposition to some traditional PPP arrangements.
Notable strengths
Mexico's leading advantage is project preparation and sustainability, ranking 4th in the region, supported by systematic project-selection procedures and financing facilities. Its project development and viability-gap financing mechanisms, land acquisition assistance and socioeconomic appraisal requirements distinguish it from regional peers. Financing ranks 5th, reflecting government support, participation by multilateral and institutional investors, and relatively favorable financing conditions. Competitive bidding and well-defined risk allocation provide additional strengths, alongside provisions that prioritize social inclusion in project selection.
Notable challenges
Mexico's weakest category is performance evaluation and impact, reflecting gaps in systematic ex-post evaluation and public reporting on operational PPP outcomes. Disaster risk management also lags, with limited requirements for risk assessment, insurance and force majeure guidance. Despite otherwise well-defined procurement procedures, the regulatory and institutional framework has shortcomings unusual for an experienced PPP market: overlapping investment frameworks, incomplete contract disclosure requirements and insufficient higher-level oversight of contract modifications. Guidance on coordination between contracting authorities and sector regulators also remains limited.
Recent progress
Mexico's overall index performance has changed little, but updated federal investment procedures in 2025 strengthened project prioritization, made a standardized cost-benefit analysis tool available, and introduced more consistent monitoring of physical and financial progress on PPPs receiving federal public financing. The revised prioritization criteria also place greater emphasis on reducing social and territorial inequalities. However, the reforms discontinued the previous systematic ex-post evaluation framework without establishing an equivalent process for selecting new projects for evaluation. These developments represent mixed progress rather than broad improvement across the PPP lifecycle.
Top five recommendations for progress
(ordered according to index category)
1
Clarify the scope of infrastructure investment frameworks and regulatory responsibilities
Establish clear criteria for determining which legal framework applies to infrastructure projects involving private participation, particularly where the 2012 PPP Law and 2026 strategic-infrastructure framework overlap. Clarify coordination procedures between contracting authorities and sector regulators under each framework, including responsibilities for service standards and tariffs.
Timeline to achieve
Medium term
Difficulty to achieve
Medium
Impact on category 1: Regulations and institutions
Mexico: current score
83.3
Score with recommendation applied
86.5
2
Strengthen contract transparency and oversight of modifications
Require the publication of complete executed PPP contracts, subject to appropriate confidentiality protections, and establish consistent higher-level approval requirements for material contract modifications. Build on existing expert-review and authorization mechanisms to strengthen transparency and accountability throughout contract implementation.
Timeline to achieve
Short term
Difficulty to achieve
Medium
Impact on category 1: Regulations and institutions
Mexico: current score
83.3
Score with recommendation applied
88.5
3
Strengthen disaster risk management throughout the PPP lifecycle
Introduce explicit requirements to assess disaster exposure and disaster risk management during PPP preparation, establish minimum disaster insurance standards and develop standardized <i>force majeure</i> guidance. Clarify procedures for notification, risk allocation, compensation and contractual adjustments following qualifying events.
Timeline to achieve
Medium term
Difficulty to achieve
Medium
Impact on category 4: Risk management and contract monitoring
Mexico: current score
54.6
Score with recommendation applied
79.6
4
Restore systematic ex-post evaluation of PPP projects
Reinstate a formal process for ex-post evaluation of operational PPPs, supported by an independent agency and standardized methodologies assessing realized costs, benefits, risk allocation and project outcomes. Establish mechanisms to incorporate evaluation findings into future project selection, appraisal and contract design.
Timeline to achieve
Medium term
Difficulty to achieve
Medium
Impact on category 5: Performance evaluation and impact (ex-post)
Mexico: current score
22.1
Score with recommendation applied
39.8
5
Standardize operational PPP performance monitoring and reporting
Establish standardized requirements for monitoring and publicly reporting operational PPP performance, including service quality, financial indicators and operational key performance indicators. Publish comparable, regularly updated information across projects, building on existing monitoring arrangements while extending reporting beyond investment execution.
Timeline to achieve
Medium term
Difficulty to achieve
Medium
Impact on category 5: Performance evaluation and impact (ex-post)
Mexico: current score
22.1
Score with recommendation applied
35.9
Assessment guidance:
Short term: achievable in months (ie, straightforward activities such as procedural updates)
Medium term: up to a year (ie, moderately involved activities such as building web platforms)
Long term: more than a year (ie, time-consuming activities such as new legislation/institutions)
Difficulty/complexity: rated as low/medium/high—often mirrors the time frame, but can differ based on how technical it is, how many resources are needed and how politically challenging it is, etc.
1. https://www.dof.gob.mx/abrirPDF.php?anio=2026&archivo=09042026-VES.pdf
2. https://dof.gob.mx/nota_detalle.php?codigo=5786977&fecha=08/05/2026
3. IJ Global
4. These involve private participation in highway construction or rehabilitation, long-term operation and maintenance, with remuneration linked to performance standards.
5. https://www.gob.mx/presidencia/es/articulos/version-estenografica-conferencia-de-prensa-de-la-presidenta-claudia-sheinbaum-pardo-del-04-de-marzo-de-2026
6. https://www.gob.mx/presidencia/prensa/el-plan-de-inversion-en-infraestructura-para-el-desarrollo-con-bienestar-contempla-en-2026-2-adicional-del-pib-y-5-6-bdp-al-2030
7. https://www.gob.mx/presidencia/es/articulos/version-estenografica-conferencia-de-prensa-de-la-presidenta-claudia-sheinbaum-pardo-del-6-de-febrero-de-2025
8. https://www.gob.mx/presidencia/es/articulos/version-estenografica-conferencia-de-prensa-de-la-presidenta-claudia-sheinbaum-pardo-del-04-de-marzo-de-2026
9. https://www.eleconomista.com.mx/politica/comisiones-senado-aprueban-iniciativa-ley-inversiones-mixtas-obras-20260407-807565.html
10. https://dof.gob.mx/nota_detalle_popup.php?codigo=5766239