Infrascope 2025/26
Honduras
Score: 46.0
out of 100
Rank: 14th
out of 26 countries
Despite having an established public-private partnership (PPP) framework and considerable concession experience, Honduras has awarded no new projects for several years. Institutional activity has focused on supervising existing concessions, while weaknesses in project preparation and risk management persist. Recent regulatory improvements and renewed political interest offer an opportunity to revitalize the PPP market, although translating these developments into new investment remains a challenge.
MACRO ENVIRONMENT
Population, 202511.0m
Source: The Economist Intelligence UnitGDP (US$), 2025$39.4bn
Source: The Economist Intelligence UnitSovereign risk rating, Oct 2026BB-
Source: S&P Global RatingsPPP INVESTMENT
Number, 2016-25*5
Source: IJ Global‡Total (US$), 2016-25$585m
Source: IJ Global‡% of all infrastructure investment, 2016-25†8%
Source: IJ Global,‡ Infralatam, Economist EnterprisePPP INVESTMENT BY SECTOR (US$), 2016-25
Transport$134m
Renewables$251m
Social infrastructure$200m
Policies and institutions
Honduras's PPP framework is governed by the Law for the Promotion of Public-Private Partnerships (2010) and its implementing regulations (2011). Responsibilities are divided among three main institutions. The Superior PPP Council provides strategic coordination and approves key project decisions, while the Specialized Technical Unit for PPP Projects (UTEP-APP), within the Ministry of Finance, supports project identification, evaluation, structuring and procurement. The Superintendency of Public-Private Partnerships (SAPP) independently regulates and supervises contractual compliance, particularly where no sector-specific regulator exists. This institutional structure emerged from a major restructuring in 2019, when the government dissolved the former PPP promotion agency, COALIANZA, and redistributed its responsibilities.1
Recent market developments
Honduras has considerable experience with PPP concessions, but new project development has stagnated. The Ministry of Finance's official portfolio comprises 11 historically awarded contracts, signed between 2012 and 2017, with eight projects still operational in 2025.2,3 These span transport, ports, government buildings and urban infrastructure, while renewable-energy projects account for much of the country's broader privately financed infrastructure investment. Although no new PPP contracts have been added to the official portfolio in recent years, existing concessions continue to generate investment and require ongoing supervision. Recent activity has therefore focused on implementing and managing established projects rather than expanding the PPP pipeline, despite the country's relatively comprehensive institutional framework.
Political and public support
Political support for PPPs has become more explicit following the change of administration in January 2026. The previous government's 2022-26 development plan contained no clear PPP agenda, while members of its governing party had sought to repeal the PPP Law in 2022. By contrast, the new administration's published policy program proposes reviewing existing PPP contracts, establishing a National Council for PPP Administration, and pursuing PPP arrangements for natural gas infrastructure and renewable energy development.4 These proposals suggest renewed political interest, but broader multiparty support remains limited, and previous controversies surrounding individual concessions have generated political opposition. The new administration's proposals have yet to translate into enacted reforms or new PPP awards.
Notable strengths
Honduras performs relatively well in Regulations and institutions, scoring 80.0 against a regional average of 70.8. Its clearly defined PPP institutions provide a foundation for project development and independent regulatory oversight. Contract management is another comparative strength, ranking joint fifth regionally, supported by established supervision and compliance procedures. Honduras also ranks joint first in contingent-liability management, with standardized fiscal-risk methodologies and regular assessment and reporting of government exposures arising from PPP contracts.
Notable challenges
Honduras faces significant weaknesses in project selection, ranking 20th regionally, with limited requirements for needs assessments and systematic prioritization. Environmental and social sustainability considerations are also insufficiently integrated into project preparation. Meanwhile, risk management and contract monitoring is the country's weakest category relative to the regional average, particularly because of substantial gaps in disaster risk preparedness, including risk assessments, insurance requirements and force majeure guidance. Finally, despite stronger oversight of contract amendments, transparency around contract changes and renegotiations remains limited.
Recent progress
Honduras has made modest regulatory progress on contract oversight. A 2024 regulation established clearer procedures for sanctioning noncompliance by PPP operators,5 while the 2025 budget strengthened independent oversight by explicitly requiring SAPP to authorize or reject contractual amendments.6 These measures build on existing supervision arrangements rather than representing a broader overhaul of the PPP framework. The administration that took office in January 2026 has also signaled greater interest in PPP development, although this has yet to translate into new project awards.
Top five recommendations for progress
(ordered according to index category)
1
Strengthen project prioritization and appraisal
Establish clear criteria for prioritizing PPPs and require needs assessments before project selection. Strengthen project appraisal through published methodologies and standardized tools for cost-benefit, fiscal affordability and value-for-money assessments, ensuring consistency with broader public investment procedures.
Timeline to achieve
Medium term
Difficulty to achieve
High
Impact on category 2: Project preparation and sustainability
Honduras: current score
40.9
Score with recommendation applied
57.1
2
Integrate climate and social sustainability into PPP preparation
Strengthen PPP selection and preparation requirements to incorporate national climate commitments, community consultation and social inclusion objectives. Establish clear criteria addressing gender equity, local employment, and small-business participation to ensure projects deliver broader environmental and social benefits.
Timeline to achieve
Short term
Difficulty to achieve
Medium
Impact on category 2: Project preparation and sustainability
Honduras: current score
40.9
Score with recommendation applied
58.1
3
Develop and publish a forward-looking PPP pipeline
Establish and regularly update a publicly accessible pipeline of prospective PPP projects, identifying their sectors, development stages and anticipated procurement timelines. This would improve investor visibility, support market engagement and help translate government infrastructure priorities into potential transactions.
Timeline to achieve
Short term
Difficulty to achieve
Low
Impact on category 4: Risk management and contract monitoring
Honduras: current score
37.7
Score with recommendation applied
44.0
4
Strengthen disaster risk management in PPPs
Establish requirements for assessing disaster and environmental risks to PPP infrastructure, securing appropriate catastrophic-risk insurance and incorporating standardized <i>force majeure</i> provisions into contracts. These should clarify qualifying events, responsibilities, compensation and procedures for managing disruptions and recovery.
Timeline to achieve
Medium term
Difficulty to achieve
Medium
Impact on category 4: Risk management and contract monitoring
Honduras: current score
37.7
Score with recommendation applied
62.7
5
Establish systematic ex-post evaluations and feedback mechanisms
Build on SAPP's existing supervisory capacity by establishing a project-level mandate, independent institutional remit and methodology for comprehensive ex-post evaluations of operational PPPs. Establish a process for findings on project outcomes to inform future project selection, structuring and procurement.
Timeline to achieve
Medium term
Difficulty to achieve
Medium
Impact on category 5: Performance evaluation and impact (ex-post)
Honduras: current score
26.5
Score with recommendation applied
38.7
Assessment guidance:
Short term: achievable in months (ie, straightforward activities such as procedural updates)
Medium term: up to a year (ie, moderately involved activities such as building web platforms)
Long term: more than a year (ie, time-consuming activities such as new legislation/institutions)
Difficulty/complexity: rated as low/medium/high—often mirrors the time frame, but can differ based on how technical it is, how many resources are needed and how politically challenging it is, etc.
1. https://www.tsc.gob.hn/web/leyes/PCM-064-2019.pdf
2. https://www.sefin.gob.hn/wp-content/uploads/2020/liquidacion2019/8_Informe_Anual_de_Alianzas_Publico_Privadas_2019.pdf
3. https://www.sefin.gob.hn/wp-content/uploads/2026/04/Informe-ANUAL-APP-2025.pdf
4. https://www.sefin.gob.hn/wp-content/uploads/2026/06/Plan-de-Gobierno-Juntos-Vamos-a-Estar-Bien-2026-2030.pdf
5. https://www.sapp.gob.hn/en/_files/ugd/c9b6ca_967e85f18feb472cb1972acd49c735ca.pdf
6. https://www.tsc.gob.hn/web/leyes/Decreto-4-2025.pdf